In SAP PM as at ECC6.0 EhP6, what is the purpose of "Free Material Assignment" ?
(only one answer)
A) Allows the use of Material BOM with this BOM usage.
B) Ensure the right Material BOM with this usage is assigned as Construction Type.
C) Ensure the right Material BOM with this usage is assigned as Assembly.
D) Define the BOM Usage valid for the PM application.
E) Disallow manual entry of components without selecting from the BOM.
.
Answer: E
If Blank, you cannot freely enter a material in the Task List
If set to Usage "4", freely entered material in the Task List will be generated as a Standard BOM with this BOM Usage.
(only one answer)
A) Allows the use of Material BOM with this BOM usage.
B) Ensure the right Material BOM with this usage is assigned as Construction Type.
C) Ensure the right Material BOM with this usage is assigned as Assembly.
D) Define the BOM Usage valid for the PM application.
E) Disallow manual entry of components without selecting from the BOM.
.
Answer: E
If Blank, you cannot freely enter a material in the Task List
If set to Usage "4", freely entered material in the Task List will be generated as a Standard BOM with this BOM Usage.