In SAP PP as at ECC6.0 EhP6, which of the following Planning area uses the Rough-Cut Capacity Profile ?
(only one answer)
A) Sales and Operations Planning.
B) Master Production Scheduling.
C) Long Term Planning.
D) Material Requirement Planning.
E) Capacity Requirement Planning.
.
(only one answer)
A) Sales and Operations Planning.
B) Master Production Scheduling.
C) Long Term Planning.
D) Material Requirement Planning.
E) Capacity Requirement Planning.
.
Answer: A
ReplyDeleteSOP do not use Routing but RCCP to calculate rough capacity.