In SAP PP as at ECC6.0 EhP6, which of the following creation scenarios are correct for PP BOM and Routing ?
(more than one answers)
A) CS01 can save a BOM without a Plant.
B) CS01 can save a BOM without a Material.
C) CA01 can save a Routing without a Plant.
D) CA01 can save a Routing without a Material.
E) CA01 can save a Routing without a Plant and without a Material.
.
(more than one answers)
A) CS01 can save a BOM without a Plant.
B) CS01 can save a BOM without a Material.
C) CA01 can save a Routing without a Plant.
D) CA01 can save a Routing without a Material.
E) CA01 can save a Routing without a Plant and without a Material.
.
Answer: A, D
ReplyDeleteCS01 initial screen must have Material, BOM usage, and Key Date
CA01 initial screen must have Plant and Key Date.