In SAP PP as at ECC6.0 EhP6, in which for following is the "Working Area" used to determine the scope of work for PP Master Data ?
(only one answer)
A) BOM.
B) Routing.
C) Production Version.
D) Engineering Workbench.
E) Product Structure Browser.
.
(only one answer)
A) BOM.
B) Routing.
C) Production Version.
D) Engineering Workbench.
E) Product Structure Browser.
.
Answer: D
ReplyDeleteIMG - Production - Basic Data - Engineering Workbench - Edit Working Areas.
CEWB in the Application