This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, December 20, 2016

Question no 3327 : PP Working Area

In SAP PP as at ECC6.0 EhP6, in which for following is the "Working Area" used to determine the scope of work for PP Master Data ?

(only one answer)

A)  BOM.
B)  Routing.
C)  Production Version.
D)  Engineering Workbench.
E)  Product Structure Browser.
.

1 comment:

  1. Answer: D

    IMG - Production - Basic Data - Engineering Workbench - Edit Working Areas.
    CEWB in the Application

    ReplyDelete