In SAP PP as at ECC6.0 EhP6, one can execute a Forecasting Run in which of the following areas in the PP module ?
(more than one answers)
A) SOP Planning Table.
B) SOP Product Group.
C) Planned Independent Requirement.
D) Material Master Forecasting data view.
E) Collective Stock Requirement List.
.
(more than one answers)
A) SOP Planning Table.
B) SOP Product Group.
C) Planned Independent Requirement.
D) Material Master Forecasting data view.
E) Collective Stock Requirement List.
.
Answer: A, C, D
ReplyDeleteB) SOP Product Group is a master data only
E) Collective MRP and S/R list do not functions for executing Planning