In SAP MM as at ECC6.0 EhP6, which of the Purchasing Document can be saved without a Plant ?
(more than one answers)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
(more than one answers)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
Answer: B, D
ReplyDeleteB) RFQ without Plant possible as it is purchasing strategy to request a price from vendors for all plants and it is a negotiation strategy.
ReplyDeleteD) RFQ without plant may end up to be converted to a Central Contract without plant.