In SAP PM as at ECC6.0 EhP6, which of the following activities are executed when performing a TECO on the Maintenance Order ?
(more than one answers)
A) Set Deletion Flag to Purchase Requisition item.
B) Set Deletion Flag to Purchase Order item.
C) Set Deletion Flag to the Reservation item.
D) Set Deletion Flag to the RFQ item.
E) Set Deletion Flag to the Capacity Load.
.
(more than one answers)
A) Set Deletion Flag to Purchase Requisition item.
B) Set Deletion Flag to Purchase Order item.
C) Set Deletion Flag to the Reservation item.
D) Set Deletion Flag to the RFQ item.
E) Set Deletion Flag to the Capacity Load.
.
Answer: A, C
ReplyDeleteFunctions of TECO:
ReplyDelete. Set deletion flag to PR and Reservation.
. Release capacity load to Work Centers.
. Creation Settlement Rule.
. Limited ability to change the Maintenance Order.