In SAP PM as at ECC6.0 EhP6, the system status GMPS in the Maintenance Order is updated when which of the following are performed ?
(more than one answers)
A) All components assigned to the Order have been fully goods issued.
B) Partial goods issue of any components assigned to the Order.
C) Confirmation of any operation in the Order.
D) Goods receipt of Non-Stock Purchase Order assigned to the Order.
E) Service Entry sheet entered for External Services Purchase Order from the Order.
.
(more than one answers)
A) All components assigned to the Order have been fully goods issued.
B) Partial goods issue of any components assigned to the Order.
C) Confirmation of any operation in the Order.
D) Goods receipt of Non-Stock Purchase Order assigned to the Order.
E) Service Entry sheet entered for External Services Purchase Order from the Order.
.
Answer: B, D
ReplyDeleteA, B) Any partial goods issue will update the Maintenance Order system status to GMPS (regardless of planned or unplanned material withdrawal).
ReplyDeleteC) Operation Confirmation updates the system status 'PCNF' (Partial confirmation) or 'CNF' (Full confirmation) to the Operation or Header system status. (not GMPS)
ReplyDeleteD) All Goods Receipt of Non-Stock PO which is linked to the Maintenance Order (Partial or Complete) will update Maintenance Order.
ReplyDeleteE) Only Service Entry Approval which generates the Material Document will set the system status to GMPS.