Question no 3047 : Creation of Shipment cost document

In SAP LE Transportation as at ECC6 EhP6, what influencing when Shipment cost document can be created for a Shipment document ?

(only one answer)

A)   Shipment Type.
D)   Shipping Type.
C)   Shipment Cost Type.
D)   Planning Status in the Shipment Document.
E)   Pricing Procedure.
.

1 comment:

  1. IMG - Logistics Execution - Transportation - Shipping Costs - Shipment Cost Document - Shipment Cost Type and Item Category (Control Data Block, select the Overall Planning Status required before Shipment Cost Document can be created using the Shipment Cost Type)