In SAP MM as at ECC6.0 EhP6, you can create Purchasing Document with reference to .... EXCEPT one of the following combination ?
(only one answer)
A) RFQ with reference to Contract.
B) RFQ with reference to Purchase Order.
C) RFQ with reference to Purchase Requisition.
D) Contract with reference to RFQ/Quotation.
E) Scheduling agreement with reference to RFQ/Quotation.
.
(only one answer)
A) RFQ with reference to Contract.
B) RFQ with reference to Purchase Order.
C) RFQ with reference to Purchase Requisition.
D) Contract with reference to RFQ/Quotation.
E) Scheduling agreement with reference to RFQ/Quotation.
.
You can create RFQ (ME41) with reference to:
ReplyDelete. another RFQ
. PR
. Contract
. Scheduling Agreement
You can create a Contract (ME31K) with reference to:
. another Contract
. PR
. RFQ/Quotation
You can create Scheduling Agreement (ME31L) with reference to:
. another SA
. PR
. RFQ/Quotation
. Contract