Question no 3061 : Manual Re-Order Point Planning Procedure

In SAP MM as at ECC6.0 EhP6, which of the following are mandatory setup for Manual Re-Order Point Planning Procedure in the Material Master for external procurement scenario ?

(more than one answers)

A)    A valid MRP type in the MRP 1 view.
B)    Re-Order level in the MRP 1 view.
C)    Safety stock in the MRP 2 view.
D)    Planned delivery time in the MRP 2 view.
E)    Fixed-Lot-Sizing key in the MRP 1 view.
.

4 comments:

  1. C) Safety Stock is optional (standard SAP material type field selection)

    ReplyDelete
  2. A, B, D) These are mandatory fields, MRP type 'VB' will ensure you have to enter the Re-Order level and the Planned Delivery Time field is also mandatory for external procurement.

    ReplyDelete
  3. E) This is a tricky one, and Lot-Sizing key is a mandatory field in the MRP 1 view but ROP do not dictate Fixed-Lot-Sizing method as a mandatory requirement for the Lot Sizing Rule. You can use L4L (EX) or with combination of minimum lot size or rounding for ROP.

    That is why this is not the answer.

    ReplyDelete