Question no 3064 : Purchasing minimal material master data requirement

In SAP MM as at ECC6.0 EhP6, to create a Purchasing document for 'Stock Procurement Scenario', the Material Master must have which of the following criterias ?

(more than one answers)

A)   Accounting data view.
B)   Valid MRP type in the MRP 1 view.
C)   Valid Procurement type in the MRP 2 view.
D)   Purchasing data view.
E)   Plant/Storage data view.
.

3 comments:

  1. A, D is correct because :
    . Minimal data view is Purchasing and Accounting (for stock procurement scenario)

    ReplyDelete
  2. B, C) This is a tricky one because MRP view is not necessary when manually creating Purchasing Documents, however if the MRP data view does exist then it must have a valid Procurement type in the MRP 2 view.
    . Procurement type 'E' (Internal) only for Production Order (error for Purchasing document)
    . Procurement type 'F' (External) no question ask if create Purchasing document.
    . Procurement type 'X' (Both) system warns that material is normally for In-house production when try to create purchasing document for the material.

    ReplyDelete
  3. E) Plant/Storage data view is generally not necessary when creating Purchasing Document.

    ReplyDelete