In SAP PM as at ECC6.0 EhP6, Non-Stock Procurement initiated from a Maintenance Order has the following characteristics ?
(more than one answers)
A) The Purchase Requisition procurement data from the MO cannot be changed using ME52N.
B) When the PR in converted to PO, PO data also cannot be changed using ME22N.
C) When changing the order quantity in the MO, the non-stock quantity in the PR will also be changed only before the Order is Released.
D) When changing the order quantity in the MO, the non-stock quantity in the PR will also be changed after the MO is Released.
E) When changing the order quantity in the MO, the non-stock quantity in the PR will also be changed after the Goods Receipt of the previous PO has been completed.
.
Answer: A, C, D, E,
A) The PR fields are all grayed out even accessing it in ME52N (except the PR Header Text and Item Text which still cannot be entered).
B) Changes to the PO data is possible.
C, D, E) Non-stock PR quantity can be changed by the changes of the MO quantity before Release, After Release of the MO as well as after the associated non-stock PO has been received.
For example:
MO non-stock qty is 1, PR is 1, PO is 1, GR is 1
MO non-stock qty change to 4, PR qty will change to 4, another PO can be converted to 3, GR is 3
(more than one answers)
A) The Purchase Requisition procurement data from the MO cannot be changed using ME52N.
B) When the PR in converted to PO, PO data also cannot be changed using ME22N.
C) When changing the order quantity in the MO, the non-stock quantity in the PR will also be changed only before the Order is Released.
D) When changing the order quantity in the MO, the non-stock quantity in the PR will also be changed after the MO is Released.
E) When changing the order quantity in the MO, the non-stock quantity in the PR will also be changed after the Goods Receipt of the previous PO has been completed.
.
Answer: A, C, D, E,
A) The PR fields are all grayed out even accessing it in ME52N (except the PR Header Text and Item Text which still cannot be entered).
B) Changes to the PO data is possible.
C, D, E) Non-stock PR quantity can be changed by the changes of the MO quantity before Release, After Release of the MO as well as after the associated non-stock PO has been received.
For example:
MO non-stock qty is 1, PR is 1, PO is 1, GR is 1
MO non-stock qty change to 4, PR qty will change to 4, another PO can be converted to 3, GR is 3