This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, January 8, 2018

Question no 3486 : MRP Plant Parameters Number Ranges

In SAP MM,PP as at ECC6.0 EhP6, which for the number Objects for Number Ranges can be set for MRP Plant Parameter ?

(more than one answers)

A)  Purchase Requisitions.
B)  Planned Orders.
C)  MRP List.
D)  Dependent Requirements.
E)  Total Requirements.
.

Answer: A, B, C, D, E

OMI2

No comments:

Post a Comment