In SAP PM as at ECC6.0 EhP6, which of the following are Scheduling Indicator appropriate for the following scheduling scenario ?
Today's date: 24/01/2018 Due for the current monthly cycle maintenance
Next planned date: 24/02/2018 which is always on the 24th of the month (next cycle)
(only one answer)
A) Time.
B) Time - Key Date.
C) Time - Factory Calendar.
D) Time - Fixed Cycle.
E) Exact Cycle.
.
Answer: B
Only 3 scheduling indicators:
For scheduling, one month is always 30 days
1) Time (If Today's date scheduling called an Due Maintenance for 24/01/2018, next cycle is 30 days which is 23/02/2018.
2) Time-Key Date (If Today's date scheduling called an Due Maintenance is 24/01/2018, ext cycle is 24/01/2018 which is every 24th.
3) Factory Calendar (If Today's date scheduling called an Due Maintenance is 24/01/2018, next cycle is counting 30 days from 24/01/2018 depending on the working days on the Factory Calendar)