Question no 3500 : Maintenance Plan Scheduling

In SAP PM as at ECC6.0 EhP6, which of the following are Scheduling Indicator appropriate for the following scheduling scenario ?

Today's date: 24/01/2018 Due for the current monthly cycle maintenance 
Next planned date: 24/02/2018 which is always on the 24th of the month (next cycle)

(only one answer)

A)  Time.
B)  Time - Key Date.
C)  Time - Factory Calendar.
D)  Time - Fixed Cycle.
E)   Exact Cycle.
.

Answer: B

Only 3 scheduling indicators:
For scheduling, one month is always 30 days
1) Time (If Today's date scheduling called an Due Maintenance for 24/01/2018, next cycle is 30 days which is 23/02/2018.
2) Time-Key Date (If Today's date scheduling called an Due Maintenance is 24/01/2018, ext cycle is 24/01/2018 which is every 24th. 
3) Factory Calendar (If Today's date scheduling called an Due Maintenance is 24/01/2018, next cycle is counting 30 days from 24/01/2018 depending on the working days on the Factory Calendar)