In SAP MM, PP as at ECC6.0 EhP6, Scope of Planning allows you to setup which of the following data sequence of planning for MRP run at the Plant level ?
(only one answer)
A) Plant + MRP Area.
B) Plant + Storage Location.
C) Plant + MRP Type.
D) Plant + MRP Group.
E) Plant + Material Group.
.
(only one answer)
A) Plant + MRP Area.
B) Plant + Storage Location.
C) Plant + MRP Type.
D) Plant + MRP Group.
E) Plant + Material Group.
.
Answer: A
ReplyDeleteOM0E