Question no 3458 : Estimated Cost in the Maintenance Order

In SAP PM as at ECC6.0 EhP6, Estimated Costs in the Maintenance Order can be entered in which System Status ?

(only one answer)

A)   Before Release.
B)   After Release before TECO.
C)   After TECO before CLSD.
D)   Anytime.
E)   It cannot be entered as it was calculated automatically.
.

Answer: A

at CRTD, you can enter the Estimated Costs via Value Category, but after Release the fields are in Display only.