In SAP MM or PP as at ECC6.0 EhP6, which of the following data fields are Required in MRP1 and MRP2 data view when MRP Type "ND" is assigned ?
(only one answer)
A) MRP Group.
B) MRP Controller.
C) Lot Size Key.
D) Planned Delivery Time.
E) Scheduling Margin Key.
.
Answer: D
Standard SAP delivers Planned Delivery Time is required entry for MRP Type "ND".
(only one answer)
A) MRP Group.
B) MRP Controller.
C) Lot Size Key.
D) Planned Delivery Time.
E) Scheduling Margin Key.
.
Answer: D
Standard SAP delivers Planned Delivery Time is required entry for MRP Type "ND".