In SAP PM as at ECC6.0 EhP6, in which of the following status where Settlement can be executed ?
(only one answer)
(A) Must be after TECO but before CLSD.
(B) Must be after REL but before CLSD.
(C) Can be at CRTD status but before TECO.
(D) As long as after TECO.
(E) As long as after REL.
.
Answer: B
Partial Settlement allows OH calculation as well as Settlement after REL status as well after after TECO but must be done before the system status CLSD.