In SAP PM as at ECC6.0 EhP6, which of the following is a Secondary Cost Element in the Maintenance Oder ?
(only one answer)
A) Stock item's Cost Element.
B) Non-Stock item's Cost Element.
C) Control Key PM01's Cost Element.
D) Control Key PM02's Cost Element.
E) Control Key PM03's Cost Element.
Answer: C
Internal labour via PM01 control key uses secondary cost element for CO posting only.
(only one answer)
A) Stock item's Cost Element.
B) Non-Stock item's Cost Element.
C) Control Key PM01's Cost Element.
D) Control Key PM02's Cost Element.
E) Control Key PM03's Cost Element.
Answer: C
Internal labour via PM01 control key uses secondary cost element for CO posting only.