This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, April 19, 2016

Question no 3122 : Production Version selection

In SAP PP as at ECC6.0 EhP6, in which of the following you can the settings for selection between automatic Production Version assignment and Manual Production Version assignmenf ?

(Only one answer) 

A)   Material Master MRP4 view.
B)   Material Master Work Scheduling view.
C)   Production Version detail.
D)   Production Scheduler Profile.
E)   Order Type dependent parameter.
.

2 comments:

  1. t-code OPL8, Planning TAB first field Production Version selection of 1 and 0 for Manual or Automatic respectively.

    ReplyDelete