In SAP PP or MM as at ECC6.0 EhP7, when creating a Material Master for MRP views with MRP type 'ND', which of the following fields are mandatory in the MRP1 and MRP 2 views ?

(only one answer)

A)   Lot size key.
B)   Planned delivery time.
C)   Scheduling Margin Key.
D)   MRP Group,.
E)   Special Procurement key.
.