In SAP PP as at ECC6.0 EhP6, which of the following are minimal requirement for creating a Production Order ?
(only one answer)
A) Material Master.
B) One Operation.
C) BOM.
D) Production resource tool assignment.
E) Routing.
.
(only one answer)
A) Material Master.
B) One Operation.
C) BOM.
D) Production resource tool assignment.
E) Routing.
.
Answer: B
ReplyDeleteA) CO07 can create production order without material. For cleaning, book capacity for maintenance etc.
ReplyDeleteB, C, E) A production order can be created without BOM or Routing but must have at least one operation. T-code OPJG for default operation values.
ReplyDeleteD) PRT never necessary in operations in standard SAP.