In SAP Plant Maintenance as at ECC6.0 EhP6, assume the following scenario and deduce the next due date for the Single-Cycle Counter Maintenance Plan
Measuring Point Annual Estimate 30000 km
Single-Cycle Plan at 15000 km
Current Counter reading at 5000 km
Todays data is 15.04.2016, what is the next due date as the Maintenance Plan is scheduled ?
(only one answer)
A) 15.06.2016
B) 15.07.2016
C) 15.08.2016
D) 15.09.2016
E) 15.10.2016
.
Measuring Point Annual Estimate 30000 km
Single-Cycle Plan at 15000 km
Current Counter reading at 5000 km
Todays data is 15.04.2016, what is the next due date as the Maintenance Plan is scheduled ?
(only one answer)
A) 15.06.2016
B) 15.07.2016
C) 15.08.2016
D) 15.09.2016
E) 15.10.2016
.
Since the Annual Estimate is 30000 km and the Cycle in 15000 km, the theoretical plan due will be every 6 months. The Current Counter is now at 5000 km meaning another 10000 km next maintenance is due. 10000 km of 30000 km is 1/3 which is 4 months. The current date is 15.04.2016. Hence the next Maintenance due date is 15.04.2016 + 4 months = 15.08.2016