In SAP MRP as at ECC6.0 EhP6, which of the following MRP parameters can be found in both Plant Parameters and MRP Group Parameters ?
(more than one answers)
A) Number Ranges.
B) Planning Horizon.
C) Order Types for Planned Orders to Production/Process Orders.
D) Tolerance for Rescheduling Proposals.
E) Planning Time Fence.
.
Answer: B, C, D
ReplyDeletePlant Parameter via t-code OPPQ
ReplyDeleteMRP Group Parameters via t-code OPPR
A) Number ranges for Planned Orders, Dependent Requirements, PR can only be found in OPPQ (Plant Parameters)
ReplyDeleteB) Planning Horizon, Order Type for conversion of planned orders to PPDI/PPPI, and Rescheduling tolerances are the parameters that can be found in both OPPQ and OPPR.
ReplyDeleteOnly in OPPR (MRP Group parameters), you can find the Planning Time Fence and Roll-Forward Period.