Question no 2395 : Production BOM Component Item Category

In SAP Production Planning for Discrete Industry (PPDI), which of the following best suites the following scenario:

A wooden speaker box production facility makes a model of speaker box shaped of all sides the same which is 15cm x 15cm x 15cm; for every speaker box it requires 5 pieces of  50cm x 50cm, all such cuttings are done from 120cm x 240cm chipboards. The Procurement requirement is done by meter square but Production requirements is by how many pieces of 15cm x 15 cm requirements to be cut.

(only one answer)

A)    'N'.
B)    'L'.
C)    'R'.
D)    'C'.
E)    Not Possible.
.

1 comment:

  1. 'Variable Size' item category 'R' is used to defined requirements of dimensions either length, area, or volume. The scenario description fits this requirement. A formula is possible when defining the 'R' item category component. 3 sizes is avilable, variable size 1, 2, and 3 as well as number of units required and the calculation results in total length, area, or volume.