In SAP Plant Maintenance ECC6.0 EhP5, which of the following are valid PRTs (Production Resource Tools) which can be assigned to the General Task List Operations ?
(more then one answers)
A) Document PRT.
B) Material PRT.
C) Equipment PRT.
D) Miscellaneous PRT.
E) Measuring Point PRT.
.
(more then one answers)
A) Document PRT.
B) Material PRT.
C) Equipment PRT.
D) Miscellaneous PRT.
E) Measuring Point PRT.
.
Measuring Point PRT was added at ECC6.0 EhP3-4. This is to allow the scenario of Counter entry of Measuring Points at IW42 Overall Confirmation.