This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, April 30, 2014

Question no 2362 : Estimated Costs in Maintenance Order

In SAP PM ECC6.0 EhP5, the Estimated Cost has which of the following feature ?

(more then one answers)

A)   It can only be entered before setting the Order to Release Status.
B)   Estimated Cost can be entered at both Value Category and Cost Element level.
C)   Estimated Cost are never reported at the Cost Element level.
D)   The Estimated Costs can be switch off for each Order Type.
E)   Estimated Cost can be entered as long as the Order is not at TECO status.
.

4 comments:

  1. A, E) Estimated Costs can be entered from 'CRTD' (Created Status) until before 'REL' (Release Status) but not after that.

    ReplyDelete
  2. B, C) Estimated Costs are only entered at the Value Category level.

    ReplyDelete
  3. D) There are no related configuration to switch on or off the Estimated Costs per Order Type.

    ReplyDelete

Note: Only a member of this blog may post a comment.