In SAP ECC6.0 EhP5, in the PM module, which of the following data entry scenarios are subjected to commitment accounting ?
(more then one answers)
A) Control key "PM01" in the Maintenance Operations.
B) Control key "PM02" in the Maintenance Operations.
C) Control key "PM03" in the Maintenance Operations.
D) Item Cateogry "L" in the Maintenance Operations.
E) Item Cateogry "N" in the Maintenance Operations.
.
(more then one answers)
A) Control key "PM01" in the Maintenance Operations.
B) Control key "PM02" in the Maintenance Operations.
C) Control key "PM03" in the Maintenance Operations.
D) Item Cateogry "L" in the Maintenance Operations.
E) Item Cateogry "N" in the Maintenance Operations.
.
Answer: B, C, E
ReplyDeleteControl Key PM02, PM03 and item category "N" all result in Purchase Requisiton (external procurement) and only these scnearios are subjected to commitment accounting as at ECC6.0 EhP5.
ReplyDelete