Question no 2344 : SD Material Availability Date

In SAP ECC6.0 SD, the determination of the Material Availability Date is via which of the following ?

(only one answer)

A)    The Earliest of the Pick/Pack Time.
B)    The Latest of the Pick/Pack Time.
C)    The Start of the Transportation Lead Time.
D)    The Earliest of the Loading Time.
E)     Load Time plus Transit Time.
.