This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, April 25, 2014

Question no 2359 : After a Maintenance Order is Technically Completed.

In ECC6.0 Plant Maintenance, when a Maintenance Order is Technically Completed, which of the following systems responses are correct when you perform the respective transactions ?

A)   Conversion of Non-Stock Purchase Requisitions to Purchase Order are not allowed.
B)   Goods Receipt of Non-Stock Purchase Orders are not allowed.
C)   Invoices of Non-Stock Purchase Orders are not allowed.
D)   Changes to the Settlement Rule of the Maintenance Order is allowed.
E)   If the Maintenance Order Cost Balances are not Zero, you may not set it to Business Completion.

5 comments:

  1. A) Conversion of a Non-Stock Purchase Requisition to a Purchase Order is not allowed after the Maintenance Order has been TECOed. The system issues a message to request you to put the Purchase Order on Hold and issue an error message of BS013.

    ReplyDelete
  2. B, C ) Both Goods Receipt and Invoice Entry for the non-stock Purchase Order however are allowed, this will increase the actual costs of the Maintenance Order.

    ReplyDelete
  3. D) You can change the Settlement Rules after the Maintenance Order is TECOed. However, you must have a Settlement Rule at the point of TECO.

    ReplyDelete
  4. E) The system dis-allow settlement of any Maintenance Order with Costs Balances.

    ReplyDelete

Note: Only a member of this blog may post a comment.