Question no 1696 : Process message for Time Event Confirmation

In SAP PPPI ECC6.0, which of the following Process Messages are not Time Event Confirmation ?

(only one answer)

A)   PI_PHACT
B)   PI_PHST
C)   PI_SRACT
D)   PI_SRST
E)   PI_PHCON
.

2 comments:

  1. The following process message categories that you can use for confirmations have been predefined by SAP:

    Time event confirmations:
    .• PI_PHACT Message on activities (phase)
    •. PI_PHST Message on phase status
    •. PI_SRACT Message on activities (secondary resource)
    •. PI_SRST Message on secondary resource status

    Time ticket confirmations:
    •. PI_PHCON Time ticket confirmation for phase
    •. PI_SRCON Time ticket confirmation for secondary resource

    ReplyDelete