Question no 1689 : Confirmation of Process Orders

In SAP PPPI ECC6.0, which of the following confirmation options are not possible for Process Orders ?

(only one answer)

A)    Confirmation for Phases.
B)    Confirmation for Secondary Resources.
C)    Confirmation for Operations.
D)    Confirmation for Process Order.
E)    Confirmation via the PI-Sheet.



2 comments:

  1. In the Master Recipe, the standard values are recorded at the Phase level. Therefore, each Operations should have at least one phase for operation confirmation.

    ReplyDelete