In SAP PPPI ECC6.0, which of the following confirmation options are not possible for Process Orders ?
(only one answer)
A) Confirmation for Phases.
B) Confirmation for Secondary Resources.
C) Confirmation for Operations.
D) Confirmation for Process Order.
E) Confirmation via the PI-Sheet.
.
(only one answer)
A) Confirmation for Phases.
B) Confirmation for Secondary Resources.
C) Confirmation for Operations.
D) Confirmation for Process Order.
E) Confirmation via the PI-Sheet.
.
Answer: C
ReplyDeleteIn the Master Recipe, the standard values are recorded at the Phase level. Therefore, each Operations should have at least one phase for operation confirmation.
ReplyDelete