In SAP APO SNP ECC6.0, which of the following are not part of the SNP process flow ?
(more then one answers)
A) TLB Run.
B) Deployment Run.
C) Heuristic Planning Run.
D) CTM.
E) Release SNP results to DP.
.
(more then one answers)
A) TLB Run.
B) Deployment Run.
C) Heuristic Planning Run.
D) CTM.
E) Release SNP results to DP.
.
The sequence of SNP Process flow:
ReplyDelete1) Setup SNP Master Data and Interface.
2) Setup SNP Configuration.
3) Release DP results to SNP.
4) Perform SNP run: Heuristic, Optimization, CTM.
5) Check plan/Solve problems.
6) Finalize SNP results for PPDS.
7) Release Constraint Plan to PPDS.
8) Deployment Run.
9) TLB Run.