Question no 3903 : MRP run Master Data

In SAP MM/PP as at ECC6.0 EhP6, which of the following is not used in an MRP run when it creates a Planned Order ?

(Only one answer)

A)  Quota Arrangement.
B)  Source List.
C)  Stock Determination Rule.
D)  Scheduling Margin Key.
E)  Lot Size Key.
.

Answer: C

A) Quota Arrangement is activated when MRP usage for Quota Arrangement is activated in the MRP 2 data view (in ECC6), but this indicator is not longer available is S4 meaning there is no Material Master activation required in S4 for usage of Quota Arrangement in S4.
B) Source List can be set with MRP relevancy for each source so that MRP run will use the information to Supply creation.
C) Stock Determination Rule is used for Storage Location determination for Reservations or Orders in MIGO, and not relevant at point of MRP run for Supply determination. 
D) Scheduling Margin Key set in MRP2 view is mandatory setting when a valid MRP type is assigned to the Material, the Opening Period from the SMK is used to determine the Planned Orders Opening date. It can also be used to create Planned Orders in the Opening Period. 
E)  The Lot Size Key set in MRP1 view is used to determine the Lot Size used to create the Planned Orders in an MRP run.