This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, December 6, 2021

Question no 3900 : Stock Requirement List

In SAP MM/PP as at ECC6.0 EhP6, which of the following is not an MRP Element in a Stock Requirement List ?

(more than one answers)

A)  RFQ.
B)  Contract.
C)  Repetitive Planned Order.
D)  Production Order.
E)  Sales Order.
.

Answers: A, B

Not RFQ nor Contract.