In SAP MM/PP as at ECC6.0 EhP6, which of the following is not an MRP Element in a Stock Requirement List ?
(more than one answers)
A) RFQ.
B) Contract.
C) Repetitive Planned Order.
D) Production Order.
E) Sales Order.
.
Answers: A, B
Not RFQ nor Contract.
(more than one answers)
A) RFQ.
B) Contract.
C) Repetitive Planned Order.
D) Production Order.
E) Sales Order.
.
Answers: A, B
Not RFQ nor Contract.