Question no 3898 : Time Fence

In SAP MM/PP as at ECC6.0 EhP6, which of the following are TRUE about Time Fence ?

(more than one answers)

A)  Time fence for a material is activated via the MRP Type.
B)  Time fence for a material is activated via the MRP Group.
C)  Time fence for a material is activated via the Lot Size Key.
D)  Time fence for a material is activated via the Plant Parameter.
E)  Time fence for a material is activated via the Scheduling Margin Key.
.

Answer: A

The Firming indicator in the MRP Type will use the Time Fence.
 