In SAP MM/PP as at ECC6.0 EhP6, which of the following is used to default the Procurement Type in the MRP 2 data view in the Material Master ?
(only one answer)
A) MRP Type parameter.
B) MRP Group parameter.
C) Plant parameter.
D) Material Group parameter.
E) Material Type parameter.
.
Answer: E
Material Type config from OMS2.
(only one answer)
A) MRP Type parameter.
B) MRP Group parameter.
C) Plant parameter.
D) Material Group parameter.
E) Material Type parameter.
.
Answer: E
Material Type config from OMS2.