Question no 3897 : Data for MRP run

In SAP MM/PP as at ECC6.0 EhP6, which of the following data fields/data views contain the minimum necessary data for MRP run for external procurement material ?

(more than one answers)

A)  MRP 1 data view.
B)  MRP 2 data view.
C)  MRP 3 data view.
D)  MRP 4 data view.
E)  MRP 4 data view at the SLoc level.
.

Answers: A, B

MRP Type in MRP 1.
MRP Controller in MRP1.
Lot Size in MRP 1.
Procurement key in MRP 2. (to decide if it is External or Internal Procurement)
Scheduling data in MRP 2. (Planned delivery time is optional, lead time can also set in MM Info Record)
Scheduling Margin Key in MRP2. (mandatory in ECC but optional in S4).