In SAP MM/PP as at ECC6.0 EhP6, consider the following and deduce the MRP resulted Order Lot Size:
. Lot size key "FX'
. Fixed Lot Size 300
. Current Stock 100
. Demand 600
(Only one answer)
A) Planned Order of 600
B) Planned Order of 300, Planned Order of 300.
C) Planned Order of 300, Planned Order of 200.
D) Planned Order of 500, Planned Order of 500.
E) Planned Order of 500.
.
Answer: B
B) Gross Requirement = 600-100 = 500, Fixed lot size result in 2 Planned Orders of each 300.