In SAP PM as at ECC6.0 EhP6, which of the following correctly describes a Process Permit ?
(only one answer)
A) Permit assignment based on Maintenance Scenario.
B) User will have to assign Process Permit during Mainteannce Processing.
C) Permit is generated impromptu at the point of Maintenance Order creation.
D) Permit is activated via Class Characteristics values in the Permit matching that is in the Maintenance Order.
E) None of the above.
.
Answer: D
Process Permit is assigned with a Class and Characteristics Values, matched Maintenance Order field value will activate the Process Permit.
(only one answer)
A) Permit assignment based on Maintenance Scenario.
B) User will have to assign Process Permit during Mainteannce Processing.
C) Permit is generated impromptu at the point of Maintenance Order creation.
D) Permit is activated via Class Characteristics values in the Permit matching that is in the Maintenance Order.
E) None of the above.
.
Answer: D
Process Permit is assigned with a Class and Characteristics Values, matched Maintenance Order field value will activate the Process Permit.