In SAP PM as at ECC6.0 EhP6, which of the following the Factory Calendar can be assigned to ?
(more than one answers)
A) Maintenance Notification.
B) Maintenance Order.
C) Equipment Master.
D) Maintenance Work Center.
E) Maintenance Plan Header.
.
Answers: B, D, E
B) One of the Enhancement Package in ECC6 allows the Factor Calendar assignment to an MO so that scheduling can be based on a selected Factory Calendar for that MO (IW31/IW32/IW33).
(more than one answers)
A) Maintenance Notification.
B) Maintenance Order.
C) Equipment Master.
D) Maintenance Work Center.
E) Maintenance Plan Header.
.
Answers: B, D, E
B) One of the Enhancement Package in ECC6 allows the Factor Calendar assignment to an MO so that scheduling can be based on a selected Factory Calendar for that MO (IW31/IW32/IW33).
D) In the Capacity TAB of the Maintenance Work Center (IR01/IR02/IR03).