In SAP MM as at ECC6.0 EhP6, which of the following temporary block a vendor in the Quota Arrangement to be selected during Source Determination ?
(only one answer)
A) Delete the vendor in the Quota Arrangement.
B) Set the validity date of the vendor to be blocked.
C) Set the Quota Based Qty to a high value.
D) Click the Block indicator in the Quota Arrangement.
E) Set the Quota for that vendor to zero.
.
Answer: C
The Calculated Quota Rating is used for vendor selection. When the Quota Based Qty is a high value, the Quota Rating will be a low value hence the vendor is not selected.
(only one answer)
A) Delete the vendor in the Quota Arrangement.
B) Set the validity date of the vendor to be blocked.
C) Set the Quota Based Qty to a high value.
D) Click the Block indicator in the Quota Arrangement.
E) Set the Quota for that vendor to zero.
.
Answer: C
The Calculated Quota Rating is used for vendor selection. When the Quota Based Qty is a high value, the Quota Rating will be a low value hence the vendor is not selected.