This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, May 19, 2021

Question no 3842 : Purchasing Processing Time

In SAP MM/PP MRP as at ECC6.0 EhP6, how is the Purchasing Processing Time is set ?

(only one answer)

A)  Material Master MRP 2 data view.
B)  MRP Group parameter.
C)  Plant parameter.
D)  Scheduling Margin Key.
E)  Purchasing Info Record.
.

Answer: C

OPPQ