In SAP MM/PP as at ECC6.0 EhP6, which of the following are TRUE when:
Opening period = 0 days
Planned Delivery Time = 5 days
GR Processing time = 0 days
(more than one answers)
A) Opening date = Order finish date.
B) Opening date = Order start date.
C) Order start date = Order finish date.
D) Stock available date = Order finish date.
E) Opening date = Stock available date.
.
Answers: B, D
Opening date + Opening period = Order start date
Order start date + Planned delivery time = Order finish date
Order finish date + GR processing time = Stock available date
Opening period = 0 days
Planned Delivery Time = 5 days
GR Processing time = 0 days
(more than one answers)
A) Opening date = Order finish date.
B) Opening date = Order start date.
C) Order start date = Order finish date.
D) Stock available date = Order finish date.
E) Opening date = Stock available date.
.
Answers: B, D
Opening date + Opening period = Order start date
Order start date + Planned delivery time = Order finish date
Order finish date + GR processing time = Stock available date