In SAP MM/PP as at ECC6.0 EhP6, which of the following variables are required in the Material Master for automatically calculating Re-Order Point ?
(more than one answers)
A) Service Level.
B) Safety Stock.
C) Consumption Values.
D) Replenishment Lead Time.
E) Opening period.
.
Answers: A, B, C, D
The following values are important for defining the reorder point:
Safety stock
Average consumption
Replenishment lead time
The following values are important for defining the safety stock:
Past consumption values (historical data) or future requirements
Vendor/production delivery timelines
Service level to be achieved
Forecast error, that is, the deviation from the expected requirements
(more than one answers)
A) Service Level.
B) Safety Stock.
C) Consumption Values.
D) Replenishment Lead Time.
E) Opening period.
.
Answers: A, B, C, D
The following values are important for defining the reorder point:
Safety stock
Average consumption
Replenishment lead time
The following values are important for defining the safety stock:
Past consumption values (historical data) or future requirements
Vendor/production delivery timelines
Service level to be achieved
Forecast error, that is, the deviation from the expected requirements