Question no 3843 : MRP run generating PR

In SAP MM/PP as at ECC6.0 EhP6, which of the following data is used to derived dates for Purchasing Requisition in MRP run ?

(more than one answers)

A)  Opening period.
B)  Purchasing processing time.
C)  Planned delivery time.
D)  GR processing time.
E)  Released period.
.

Answers: B, C, D

A) Opening period is for Planned Orders.
E) Released Period is for Production Orders.