In SAP MM/PP as at ECC6.0 EhP6, which of the following data is used to derived dates for Purchasing Requisition in MRP run ?
(more than one answers)
A) Opening period.
B) Purchasing processing time.
C) Planned delivery time.
D) GR processing time.
E) Released period.
.
Answers: B, C, D
A) Opening period is for Planned Orders.
E) Released Period is for Production Orders.
(more than one answers)
A) Opening period.
B) Purchasing processing time.
C) Planned delivery time.
D) GR processing time.
E) Released period.
.
Answers: B, C, D
A) Opening period is for Planned Orders.
E) Released Period is for Production Orders.