This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, November 8, 2017

Question no 3463 : Serial and EQ synchronization

In SAP Plant Maintenance as at ECC6.0 EhP6, which of the following settings ensure that the Serial and Equipment Number are synchronized ?

(only one answer)

A)  Serial Profile.
B)  Equipment Category.
C)  Serial Category.
D)  Serial Level.
E)  Creation Profile.
.

Answer: D

Material Master Plant/Data Storage view 2