Question no 3444 : Order Release activity in MO

In SAP PM as at ECC6.0 EhP6, which of the following activities can be set be occur at the Order Release step of the Maintenance Order via the Order Type ?

(more than one answers)

A)   Creation of PR.
B)   Creation of PO.
C)   Creation of the Confirmation No.
D)   Creation of Settlement rule.
E)   Creation of Reservation.
.

Answer: A, D, E

A, E) IMG-> PM/CS-> Maint.ServProcessing-> Maint.ServOrders-> Functions and Settings for Order Types-> Define Change Document, Collective PR, MRP Relevance

D)  IMG-> PM/CS-> Maint.ServProcessing-> Maint.ServOrders-> Functions and Settings for Order Types-> Settlement Rule: Define Time and Creation of Distribution Rule