Question no 3441 : Purchasing Document for Maintenance Order

In SAP PM as at ECC6.0 EhP6, which of the following PM-MM-Procurement Scenario is Possible ?

(more than one answers)

A)  Create manual PR with reference to the MO using ME51N.
B)  Create manual PO with reference to the MO using ME21N.
C)  Generate PR when saving an MO via IW31 for Non-Stock Material.
D)  Generate PO when saving an MO via IW31 for Non-Stock Material.
E)  Generate PR when saving an MO via IW31 for Stock Material.
.

Answer: A, B, C

D) PO Generation directly when saving an MO is never possible.
E) Item Category "L" only create Reservation and not PR or PO from saving the MO.